Completed
 

ZIWA VICTORIA PROJECT

Project Description: Extension of the lake Victoria pipe line water supply project to Tabora, Nzega and Igunga Towns.
Project Status: Completed.
Project Start Date: 23-08-2018.
Project End Date: 26-02-2020.
Project Cost: Tsh. 617,205,000,000.
Project amount Paid: Tsh 613,377,000,000.
Unpaid Amount: Tsh 3,828,000,000.
Implementor: Ministry of Water (MoW).
Fund Source: Governmnent of INDIA.
Implemention Type: Contractor.